Three Louisiana advocacy groups are asking a state judge to invalidate a Public Service Commission policy that allows certain utility projects to move through an expedited regulatory process, arguing the commission adopted it without giving the public adequate notice or an opportunity to comment.
The groups filed a petition Nov. 9 in the 19th Judicial District Court in East Baton Rouge Parish. The lawsuit challenges the commission’s “Lightning Directive,” which commissioners approved in December 2025.
The plaintiffs are the Louisiana Landowners Coalition, Louisiana Citizen Advocacy Group and Save My Louisiana Inc. The petition lists New Orleans attorney William Most, of Most & Associates, as their counsel.
The directive was introduced by then-Commissioner Jean-Paul “J.P.” Coussan during the commission’s Dec. 17, 2025, meeting. The commission’s meeting minutes show the item was listed as “Directive on Commission’s Lightning Initiative” and requested by Coussan.
The proposal created an alternative regulatory pathway for utilities seeking approval of new power-generation capacity to serve certain large or expanding customers. It allows qualifying projects to receive waivers from portions of the commission’s existing market-based mechanisms requirements, which include competitive procurement procedures.
To qualify, a project must meet five conditions, including a signed electric service agreement with a new or expanding customer, a projected need for additional power, a letter from Louisiana Economic Development supporting the customer’s interest, a contract lasting at least 15 years and a commitment to cover at least half of the fixed revenue requirement associated with the proposed capacity.
The directive also instructs commission staff to process qualifying applications on a schedule intended to allow a commission vote within eight months of filing.
What the lawsuit alleges
The plaintiffs argue the commission violated the Louisiana Constitution by adopting the directive without following procedures they say are required when the agency changes its rules.
The petition challenges the wording of the meeting agenda, which described the item only as “Directive on Commission’s Lightning Initiative.” The groups contend that description did not adequately inform the public that commissioners would consider a new regulatory pathway affecting utility approvals.
The lawsuit cites a 1977 Louisiana Supreme Court decision concerning the commission’s obligation to provide notice and a reasonable opportunity for interested parties to submit information or opinions when it changes its rules.
The groups are asking the court to declare the directive invalid, bar the commission from enforcing it and require the agency to establish written procedures for future rule changes.
The commission’s position on the directive is reflected in its regulatory filings. In an order issued Oct. 15 in a separate case involving Cleco Power, the commission described the directive as a policy adopted at its Dec. 17, 2025, meeting. The order says it provides for waivers from parts of the commission’s market-based mechanisms order when specified conditions are demonstrated.
How the policy relates to Louisiana data center projects
The directive is being used in proceedings involving two major data center developments in Louisiana: Meta’s planned project in Richland Parish and Applied Digital’s Delta Forge 1 campus in Rapides Parish.
Entergy Louisiana filed an application March 25 seeking approval for generation and transmission resources to serve a proposed large data center customer in Richland Parish. The commission’s May 14 order in docket U-37882 identifies the customer as Evest LLC and says the application was submitted under the Lightning Directive.
The application seeks certification of seven new natural gas-fired combined-cycle generating units, along with related transmission resources. The commission’s order says the project is intended to serve a hyperscale data center being developed in Richland Parish.
The May order also set the application for commission consideration at its Dec. 16, 2026, meeting. That schedule places the proposed vote before the commission’s next scheduled meeting in January 2027.
The Louisiana Public Service Commission’s docket records provide filings and updates in Entergy’s proceeding.
The directive has also been invoked in Cleco Power’s application for generation and transmission approvals related to Applied Digital’s Delta Forge 1 project. In an Oct. 15 commission order in docket U-38035, the commission said Cleco filed its application under the Lightning Directive.
Louisiana Economic Development announced in May that Applied Digital planned a $3.6 billion data center campus in Rapides Parish. The agency’s project announcement says Cleco will provide electricity to the campus, which is expected to begin initial operations in mid-2027.
The lawsuit’s potential effect on those proceedings will depend on how the court rules and whether the commission can continue using the directive while the case is pending.
State policy and other data center development
The commission’s initiative followed Gov. Jeff Landry’s September 2025 executive order establishing the Louisiana Lightning Speed Initiative. In Executive Order JML 25-102, Landry directed Louisiana Economic Development to coordinate with state agencies, including the Public Service Commission, to accelerate interagency work on economic development projects.
The order called for agencies to coordinate on policy, permitting, infrastructure, workforce and regulatory processes. The commission’s December directive was proposed as part of that broader effort.
Louisiana is also pursuing other large data center investments. Louisiana Economic Development announced in August that Amazon’s planned investment in northwest Louisiana had grown to $18 billion across three proposed campuses, including a site at Resilient Technology Park in Shreveport. The agency’s announcement describes the company’s investment plans but does not establish that the Amazon campuses are using the commission’s Lightning Directive.
The lawsuit does not determine whether any of the proposed data center projects will receive approval. It challenges the process the commission adopted for certain utility applications.